Dallas-Fort Worth Permitting & Plan Review

Opening in Dallas-Fort Worth means getting approval from the right health authority for your exact address, and in this metro that authority changes from one city limit to the next. Two anchor cities run their own programs, two counties cover much of what sits between them, and dozens of other cities run programs of their own. The steps are not secret, but they live on several different websites and phone lines, and it is easy to file with the wrong office and lose weeks. FoodClout handles the health side of permitting and plan review for restaurants across Dallas-Fort Worth, remotely. We review your plans against the rules that apply to your address, assemble a complete submittal, and manage the process with the health department until your permit is issued.

We are owner’s-side consultants. We do not work for the health department and we do not sell equipment. Our job is to get your project approved without avoidable correction cycles.

First, the right authority for your address

In Dallas-Fort Worth the health authority is set by the address, not the mailing city, and picking the wrong one is the first way openings

  • Inside Dallas city limits: City of Dallas Code Compliance, Consumer Health Division. Food establishment permit.

  • Unincorporated Dallas County and cities that contract with the county, including Duncanville, Farmers Branch, Lancaster, Rowlett and University Park: Dallas County Health and Human Services, Environmental Health Division.

  • Inside Fort Worth city limits: City of Fort Worth Environmental Services Department, Consumer Health Division. Health permit.

  • Unincorporated Tarrant County and cities that contract with the county, including the area around DFW International Airport: Tarrant County Public Health, Environmental Health.

  • Arlington, Irving, Plano and other incorporated cities: the city’s own health department where one exists.

  • Anywhere with no local health program: Texas Department of State Health Services (DSHS).

We confirm jurisdiction before anything is paid or filed.

When plan review is required

Plans are required before construction begins when a food establishment is newly constructed or extensively remodeled, and when an existing structure is converted to use as a food establishment. In Fort Worth, a change of ownership triggers plan review as well. Taking over a permitted

What we handle

Jurisdiction research and permit strategy. Before anything is filed, we map which permits your project needs, which agencies review it, and in what order, so the critical path is clear from day one. In this metro that map can include two different health authorities for two locations a few miles apart.

Health plan review preparation. We review floor plans, equipment schedules, and finish schedules against the requirements that apply to your address and flag what a reviewer will flag, before they see it. Dallas asks for two sets of plans with equipment cut sheets for everything used to receive, store, prepare and serve food, a kitchen equipment plan and finish schedules, and the proposed menu with expected meals served and operating hours. Fort Worth plans must show the proposed layout and arrangement, mechanical plans, the type of construction materials in work areas, and the type and model of the fixed equipment to be installed.

Submittal management. We assemble and file the health department package and track it through review. In Dallas, plans go to the Building Permit Center at 320 E. Jefferson Boulevard, where Plan Review and Consultation can be reached at 214-948-4480, and the plans are reviewed and stamped. In Fort Worth, plans and specifications go to the Development Services Department, Plans Examination Section, at 100 Fort Worth Trail, (817) 392-2222, and the Consumer Health Division plans reviewer can be reached at (817) 392-7255.

Corrections and resubmittals. Correction letters are normal. We interpret the comments, coordinate the responses with your architect, engineer, or contractor, and manage the resubmittal until the comments are cleared. Build to the approved plans: in Fort Worth, any alteration to approved plans must be cleared with the plan reviewer first, and in Dallas additional corrections can be required after an on-site inspection.

Health department coordination. We communicate with reviewers and inspectors on your behalf and prepare you for the pre-opening inspection once construction is complete. In Dallas, the Consumer Health Division is at 7901 Goforth Road, Dallas, TX 75238, and can be reached at 214-670-8083. In Fort Worth, the Certificate of Occupancy must be in hand before the health permit is issued, and the pre-operational inspection is scheduled with the plan reviewer at least seven days before construction is completed, at (817) 392-7255. Proof of a certified food manager is part of final approval.

The details reviewers check first

Hand sink placement gets flagged early on both sides of the metro. Dallas requires hand wash sinks every 25 linear feet without obstruction in the kitchen, utensil wash, and food preparation areas, and a door counts as an obstruction. Fort Worth requires hand sinks within 15 feet of all food preparation and dishwashing areas, in the same room and visible. A three-compartment sink is required, stainless steel in Fort Worth and sized to submerge the largest piece of equipment, plus at least one utility sink in Dallas, which may not double as a hand wash sink. Wall finishes must be smooth, rigid, easily cleanable, and light in color; Dallas lists fiberglass reinforced plastic and ceramic tile as approved finishes to a height of eight feet in the kitchen and four feet in the restrooms. Lighting must reach at least 50 foot-candles at surfaces where employees prepare food. Commercial grade equipment is required and domestic equipment is prohibited. Backflow prevention is required on devices connected to the potable water system. In Dallas, a grease interceptor is required for every food service establishment, new and existing; Development Services determines the size based on hours of operation, seating capacity, and dishware use, and the interceptor must be pumped at least every 90 days or when it reaches 25 percent full of grease and solids, with service manifests kept on site.

A note on Dallas-Fort Worth

There is no single metro health department. Dallas and Fort Worth each run their own consumer health program with its own reviewers, its own plan requirements, and its own permit, and the two counties cover the unincorporated areas and the cities that contract with them. A project in Dallas and a project in Fort Worth are two different permitting jobs that happen to share a metro name, and a multi-unit rollout across the metroplex can mean a different authority for nearly every address.

A note on drawings

FoodClout reviews, prepares, and manages. Where a jurisdiction requires drawings sealed by a licensed architect or engineer, your design team provides the seal and we make sure the sealed set says what the health reviewer needs to see. Many projects stall because the health review was an afterthought in the design. We make it a first thought.

Opening in Dallas-Fort Worth? Book a free consultation and we will map your permit path before you file anything.